Bridge – Jardin Scullion
Installation of 24 piles overhanging a stream at depths ranging from 50 to 60 feet.


In parallel with its gateway project on the Jardin Scullion site, Vistech Saguenay also has the mandate to install piles to support a bridge over a stream on the same site. This is another big project for Vistech Saguenay and Vistech Lac-Saint-Jean with delivery scheduled for the end of 2016!

For the purposes of this project, Vistech Saguenay used special heads to support the bridge structure. With such plates, this bridge will be solid!

Here is an overview of the structure to support. The team is confident to deliver everything for the end of 2016!

The first piles of the project are installed on the site of the bridge. The whole team is working hard to achieve an amazing result!

Pour du travail de qualité, faites affaires avec Vistech Saguenay! #organisation

A last glance at the completed project! This will make a beautiful bridge for Jardin Scullion visitors!
PROJECT DATE
2016
REALIZATION
EQUIPMENT AND MATERIAL
- Excavator: Yanmar Vio-20 equipped with a sun gear and a strong motor
- Piles: 24 P312L10-24 piles
- Extensions: 60 EX312L10 extensions
- Special heads with 12 ” X 12 ” X ¾ ” plate